Campaign Timeline
| Summer 2006 |
Placement of temporary classrooms (5 year
limit) |
| Fall 2007 |
Begin Capital Campaign |
| Jan-Feb 2009 |
Design Development (2 months) |
| Feb-Aug 2009 |
Construction Documents and Code Approvals |
2010-2011
School Year |
Advertise for Bids
Receive bids and negotiate contract
|
| Fall 2010 |
Commence construction |
Building on Tradition Goal:
$3,500,000.00
Current Donations and Pledges:
$2,040,000.00
Current Donations
Collected:
$1,610,000.00
|
|
|
|